The Oracle surges forth over Summer

No Commented Tuesday, December 22nd, 2009

Under: Residential Property

 2010 is certainly going to be a monumentous year for the Gold Coast, with the largest development on the eastern seaboard moving forward at a swift pace.

The next major milestone will be installation of the roof canopy on the western tower in January while the internal construction lift will be commissioned in the Eastern Tower early in the new year.

When the Grocon team comes back from the Christmas break, work will commence on the unique exterior finishes creating the colour and soul of the podium levels and boulevard precinct.

Works are underway on the Gold Coast Highway and Elizabeth Avenue to create new traffic flow as part of the preparation for the Oracle Boulevard.

The retail and commercial precinct is starting to take shape as the inter-tenancy walls are framed in the commercial spaces and glazing and paint finishes applied to the Podium.

Work has also started in the beachside park as part of the beautification of the area in preparation for the launch next year.

 

 

 